Steele Creek Projects
Included in Latest Transportation Plan
(January 16, 2017) The
Draft 2018-2027 State Transportation Improvement Program (STIP) includes
several projects in Steele Creek. (Years listed are federal fiscal
years, from October 1 of the previous calendar year through
September 30 of the year listed.)
Widening Highway 160:
The previous STIP
included funds for widening Highway 160 north of South Tryon Street
in 2022 ($15,650,000) and 2023 ($15,650,000). The new STIP includes
$31,300,000 for construction in 2022, which suggests the plan is to
complete construction in one year rather than two.
The new plan also
includes widening of Highway 160 south of South Tryon Street in
2022 as well as improvements to the Highway 160/Hamilton Road
intersection, as described in the updated story below.
Project
2017
2018
2019
2020
2021
2022
Improvements
to Hwy 160/Hamilton Rd intersection
ROW
$315,000
Construction
$1,300,000
Widen Hwy 160 from
Shopton Rd W to S Tryon St
ROW $500,000
Utilities $2,500,000
Construction $21,700,000
Widen Hwy 160 from S Tryon St to SC
line
ROW $3,100,000
Utilities $4,600,000
Construction $31,300,000
Bridge on Shopton Road over Coffey Creek:
This bridge was
built in 1975 and is considered structurally deficient and
functionally obsolete. The STIP calls for $120,000 for right-of-way
acquisition in 2020 and $1,200,000 for construction in 2021.
Roundabout at
Shopton Road and Beam Road:
This project will
convert the existing four-way stop intersection into a single lane
roundabout. Improvements will include crosswalks, new sidewalks,
planting strips, pedestrian refuge islands, landscaping, street
lighting, and bike lanes.
The existing
intersection creates vehicle delays and congestion. It is also very
hard for pedestrians and bicyclists to cross the street. The
proposed roundabout will reduce congestion and improve pedestrian
and bicyclist crossings. The roundabout will accommodate existing
and future vehicular traffic projections and make it easier for
bicyclist and pedestrians to cross all legs.
The STIP calls for $550,000 for right-of-way acquisition,
which is currently underway, and $1,733,000 for construction
beginning in fall 2017. The intersection of Shopton and Beam Road will close
for approximately four to five weeks, and traffic will be detoured.
This bridge was
built in 1986. The STIP calls for $270,000 for right-of-way
acquisition in 2021 and $2,700,000 for construction in 2022.
I-77 Toll Lanes
The STIP also calls for widening I-77 to ten
lanes by constructing managed lanes (toll lanes) from I-485 (Exit 1)
to I-277/NC 16 (Brookshire Freeway) (exit 11). Right-of-way and
utility relocation would begin in 2024 and construction would begin
in 2027. Since this project is scheduled to begin after the first
five years of the STIP, funding is not considered committed and is
subject to reprioritizing.
The following story
was posted on January 8 and has been updated to show construction
for the widening of Highway 160 in 2022 rather than 2022 and 2023.
Widening Highway 160
to State Line is Part of Latest Plan
(January 8, 2017)
The
North Carolina Department of Transportation (NCDOT)
released its Draft 2018-2027 Statewide Transportation Improvement
Program (STIP) last week, and it includes the widening of Highway
160 (Steele Creek Road) south of South Tryon Street to the South
Carolina state
line. NCDOT plans to issue the final approved STIP in June 2017.
The latest plan calls
for right-of-way purchase and utility relocation in 2020 and
construction beginning in 2022. This is the same schedule as the
widening of Highway 160 north of South Tryon Street approved two
years ago. This means that construction on the entire length of
Highway 160 from Shopton Road West to the South Carolina state line
is scheduled to begin as one project in 2022.
The
section south of South Tryon Street was not listed at all in the
previous, 2016-2025 STIP, so this is a significant improvement in
the priority for Steele Creek Road.
Projects scheduled to
begin in the first five years of the STIP are considered committed,
and not subject to future reprioritization. Thus all Highway
160 projects will be committed once the final STIP is approved later
this year.
The approved
2016-2025 STIP included two committed projects:
Intersection of
Highway 160 (Steele Creek Road) and Hamilton Road
Widen
intersection of NC Highway 160 (Steele Creek Road) and Hamilton Road
for additional capacity consistent with the future Steele Creek Road
cross section.
Some turn lanes have been added
at this intersection by a
developer, and
Lennar Homes will be required to make additional
improvements to accommodate additional traffic expected to be
generated by its new residential development under construction near the
intersection of Hamilton Road and Smith Road.
Highway 160 (Steele Creek Road) from Shopton Road W to S Tryon Street
This 4.2 mile widening project extends along Steele
Creek Road from Shopton Road West to South Tryon Street (NC Highway 49) in
Charlotte. Improvements include widening the existing roadway from
two (2) lanes to four (4) lanes with a grassy median and installing bike lanes and
sidewalks.
The Draft
2018-2027 STIP includes the following project
Highway 160 (Steele Creek Road) from S Tryon Street
to the South Carolina State Line
This 2.2 mile widening project extends along Steele
Creek Road from South Tryon Street (NC Highway 49) to the South Carolina
state line. Improvements include widening the existing roadway from
two (2) lanes to four (4) lanes with a grassy median and installing bike lanes and
sidewalks. Developers have provided improvements adjacent to the
RiverGate shopping complex.
According to the
Lake Wylie Pilot, Highway 160 is South Carolina will be widened from
two lanes to five from Gold Hill Road to the North Carolina state
line. "Right-of-way acquisition should begin in 2016 for the $8.8
million project. The construction at S.C. 160 and Gold Hill Road is
being done by SCDOT. Construction on the rest should come in 2017."
CRTPO issued the
following statement with the release of the Draft STIP:
NCDOT Releases Draft 2018-2027 Statewide Transportation Improvement Program (STIP)
NCDOT released its draft 2018-2027
Statewide Transportation Improvement Program (STIP) on
January 4, 2017. This document summarizes initial projects
that have been identified for funding and implementation
over the next ten years. Its release is just the beginning
of a continued effort over the next several months by CRTPO
staff and TCC members to review the projects and assess the
information for accuracy.
This step also triggers a
variety of upcoming public involvement efforts and financial
analysis at the local and state levels. NCDOT’s Board of
Transportation will adopt the STIP in June, and CRTPO is
charged with adopting their local version, known as the
2018-2027 TIP by August 2017. The TIP identifies the
region’s allocation of transportation resources among the
various capital and operating needs of the area, based on a
clear set of short-term transportation priorities. It also
identifies the strategies that CRTPO and NCDOT plan to
undertake to implement the projects within this ten-year
timeframe.
Robert Cook,
Secretary of CRTPO, will be one of the speakers at the 2017 Steele
Creek Residents Association annual meeting and will give an update
on the prioritization of Highway 160 projects.
Stuart Basham, NCDOT Division 10
Planning Engineer, and other NCDOT staff also will be at the meeting
to answer questions about highway improvement and maintenance
projects.
The Steele Creek
Residents Association meeting will be on Thursday, February 23
beginning at 6:30 PM at Christ the King Church (13501 South Tryon
Street).